Legal approvals for hydro and renewable energy projects: centre and state (overview)

By ASC Solicitors & Advocates Published Updated 3 min read

In short

Hydro and renewable energy projects in India need approvals from both the Centre and the State. At State level, the developer usually needs project allotment or an implementation agreement, land permissions and local consents. At central level, depending on the project, it may need environmental clearance, forest clearance, wildlife clearance and – for certain hydro schemes – concurrence of the Central Electricity Authority. Grid connectivity and a power purchase agreement complete the picture. The exact list depends on the technology, size, location and State policy.

Why both Centre and State matter

Electricity is on the Concurrent List of the Constitution, so both Parliament and State legislatures make laws on it. Land, water within the State and local government are largely State subjects, while environment and forest approvals are granted by the Centre. A project therefore moves through two sets of approvals at the same time.

State-level approvals (typical)

Approval What it does
Project allotment / MoU / implementation agreement Gives the developer the right to develop the project on the State's terms (for hydro, under the State hydro policy)
Land permissions Purchase or lease of private or government land; permission where State law restricts land transfers (for example, Section 118 of the Himachal Pradesh Tenancy and Land Reforms Act, 1972)
Water use and riparian permissions For hydro projects, use of river water
Pollution control consents Consent to establish and consent to operate from the State Pollution Control Board
Local consents Panchayat and gram sabha consents, where required
State transmission connectivity and PPA with State utility Evacuation of power and sale, with tariff approval by the State Electricity Regulatory Commission where needed

Central approvals (depending on the project)

Approval When it is typically needed
Environmental clearance (EIA Notification, 2006) For project categories listed in the schedule, including many hydro projects above certain capacities
Forest clearance (Van (Sanrakshan Evam Samvardhan) Adhiniyam, 1980) Where forest land is used
Wildlife clearance Where the project is in or near a protected area or eco-sensitive zone
CEA concurrence (Electricity Act, 2003, Section 8) For hydro schemes above the cost threshold notified by the Central Government
Inter-State water and dam safety matters For projects on inter-State rivers and large dams
Inter-State transmission connectivity Where power is evacuated through the inter-State network

How the approvals usually line up for a hydro project

  1. AllotmentThe State allots the project and signs an MoU or implementation agreement.
  2. Surveys and DPRThe developer prepares the detailed project report.
  3. Clearances in parallelEnvironmental, forest and, where needed, wildlife clearances; CEA concurrence of the DPR if required.
  4. LandPrivate land purchased or leased; forest land diverted; government land allotted.
  5. Connectivity and PPAGrid connectivity and a power purchase agreement; tariff approval where needed.
  6. Construction and operation consentsConsent to establish and then to operate, and compliance with clearance conditions.

Points for investors and lenders

  • Check the conditions, not just the approval. Clearances come with conditions; breach can lead to suspension.
  • Check timelines in the State agreement. Missed milestones can lead to penalties or termination.
  • Check the land position on the ground. Local disputes are a common cause of delay.
  • Watch State policy changes. Hill States have revised hydro and land policies over time.

The firm gives legal advice on these approvals and agreements. It does not assess a project's commercial viability or recommend investments.

This article is a general overview of Indian law, not legal advice.

Common questions

Do solar projects need environmental clearance?

It depends on the project and the current notifications; many solar PV projects have not been listed in the schedule to the EIA Notification, 2006, but State rules, forest land and other factors can still require approvals. Check the position for the specific project.

Who allots hydro projects in the hill States?

Usually the State Government, under its hydro policy, through a competitive process or a memorandum of understanding, followed by an implementation agreement setting out the developer's obligations.

What happens if a project needs forest land?

Use of forest land for non-forest purposes needs prior approval of the Central Government under the Van (Sanrakshan Evam Samvardhan) Adhiniyam, 1980, usually in stages, with conditions such as compensatory afforestation. Rights of forest dwellers under the Forest Rights Act, 2006 must also be settled.

Laws and official sources (5)

ASC Solicitors & Advocates

Prepared by the advocates of ASC Solicitors & Advocates, New Delhi. General information about Indian law, not legal advice.

Disclaimer

The Bar Council of India does not permit advocates to solicit work or advertise. By clicking "I agree", you confirm that:

ASC provides legal services only. Nothing on this website is investment, financial or tax advice, or a recommendation to invest.

Full text: Disclaimer